Oakville Southeast Wastewater Treatment Plant Headworks Upgrades  
Location: Oakville, ON  |  Completed: April 2017
Project Scope:
Upgrades to the Existing Wastewater Treatment Plant Including:

-The construction of a new Screening Facility
-Vortex Grit Removal Facility with a Grit Basement
-Flow Distribution Chamber and a Conveyance Channel to Plant 1, new channel from the Inlet Chamber to the new Screenings Facility
-New channel from the new Screenings Facility to the new Flow Distribution Chamber
-A new Hauled Sewage Pad
-Odour Control System for the new Screenings Building
-Removal and replacement of the Primary Clarifier and the Aeration Tank
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
Lorne Thomas Pumping Station  
Location: Aliston  |  Completed: Fall 2017
Project Scope:
Lorne Thomas Pumping Station

Pumping station construction from empty field to service new residential housing development. The project consists of the installation and construction of a new pumping station including the installation of three dry pit submersible sewage pumps, all process piping and valving, the installation of ventilation equipment, monorail lifting system, process instrumentation, and a standby natural gas generator set. The project also consisted of the installation of all electrical and SCADA control system.
   
   
   
   
   
   
   
   
   
   
   
   
   
   
St Thomas WWTP Aeration Upgrade  
Location: St Thomas  |  Completed: Winter 2017
Project Scope:
The Project Consists of the removal of two (2) blowers from the blower building and the removal of the existing aeration system and piping in Plants 2 and 3. The installation of two (2) Turbo Blowers and ceramic disc diffuser systems and piping for Plants 2 and 3. The project also includes various upgrades associated with the aeration system upgrades including mechanical piping, fittings, valving, and electrical work.
   
   
   
   
   
   
   
   
   
   
Beaver Creek Sewage Pumping Station  
Location: Waterloo  |  Completed: Sept 2015
Project Scope:
The project involved site modifications which included re-routing a 200mm diameter gravity sewer around the existing wet well, new water service, new hydrant, and additional asphalt for servicing the new valve chamber. Wet well modifications including the replacement of all inlet slide gates and level controls, and modifications to ladders, benching and piping in order to install larger pumps. Control building upgrades including the replacement of the existing generator, fuel system upgrades, and replacement of the PLC and MCCs. The installation of a new cast-in-place reinforced concrete valve chamber structure with flat roof, with motorized control valves, manual isolation valves, horizontal check valves, and flowmeters to monitor and control the flow of sewage through the pumping station in an operator friendly environment, with stairway access. The project also involved forcemain connections to the new valve chamber and the removal of the existing flow meter chamber and original buried forcemain piping.
   
   
   
Morningside  
Location: Baden  |  Completed: Winter 2016
Project Scope:
The Project Consists of the supply, installation, testing and commissioning of temporary pumping station bypass system, temporary winterization system (insulation, heat tracing) of
bypass piping/pumps to ensure freezing protection, new stainless steel piping, pipe supports, hangers and valves inside pumping station. The removal/demolition of existing slide gates, and replacement with new ones. The project also consisted of various minor electrical upgrades, PLC programming and integration services for new flow meter and relocated level sensors and the ccommissioning of station upgrades and removal of temporary bypass system.

   
   
   
   
   
   
Kleinburg Water Pollution Control Plant Upgrades  
Location: Kleinburg, ON  |  Completed: Spring 2017
Project Scope:
The project consists of modifications to the existing flow diversion storage tank including extending the existing diffuser piping and the removal of the existing chlorine contact tank.

The removal of the existing coarse bubble diffusers in the aeration tanks of the circular secondary treatment plant, replacing with new fine bubble diffusers and the removal and replacement of the existing circular clarifier.

The project also included the removal of the existing walls at the sludge holding tanks including sluice gates, piping, pipe supports, New helical scum skimmers in the rectangular secondary clarifiers, the design, supply and installation of the insulated covers at the rectangular secondary clarifiers and the removal of the existing water flushing system and replacement with new air scouring/flushing system.

   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
Medora Street Wastewater Treatment Plant Upgrades  
Location: Port Carling  |  Completed: 2014
Project Scope:
New Operations Building, including;

- Process tankage for biological and membrane filter treatment
- Existing process tank modifications for solids processing
- Modifications to existing Control Building
- Yard piping and new access road
- Septage/haulage waste receiving station with a VFD equipped submersible chopper pump
- 2 train biological treatment system, each train consisting of 3 process tanks
- Operations building contains mechanical screening units, permeate pump skid, UV disinfection system, aeration blowers, motor control center, chemical and electrical room.
- New chemical feed pumps and lines for handling coagulant and alkalinity supplements, and membrane cleaning chemicals(sodium hypochlorite and citric acid)
- Electrical power supply upgrade, including step down transformer and emergency generator

   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
   
Ontario Road Sewage Pumping Station Upgrades  
Location: Welland, Ontario  |  Completed: 2016
Project Scope:
The project consists of architectural/structural works, new raw sewage pumps, process piping, and valves, new building plumbing systems, new electrical equipment, including MCC, equipment controllers, transformer, control panel and PLC, new precast generator building complete with new standby diesel generator, diesel fuel tank, etc.
The project also involves the installation of new secondary transformer and service, electrical duct bank/conduits and wiring, construction of new yard equipment support pads, asphalted drive area surrounding the new generator soundproofed building.

   
   
   
   
   
   
   
   
   
   
   
   
Kleinburg North Pumping Station  
Location: Kleinburg, Ontario  |  Completed: 2016
Project Scope:
New Sewage Pumping Station - Above grade structure and wet well/dry pit.

Installation of multiple submersible pumps and related process piping, valves, flowmeters, VFD's, odour control unit and 100 kW diesel generator.
   
   
   
   
   
   
   
   
   
   
   
   
   
Vauxhall Water Pollution Control Plant  
Location: London, Ontario  |  Completed: September 2011
Project Scope:
Construction of new Inlet Works Building and Return Activated Sludge/Waste Activated Sludge Pumping Station Upgrades. Modifications to existing systems including:
- Reconfiguration of Yard Piping
- Inlet Distribution
- Bypass Chambers
- New Platform in Pump Station
- New Component and Modifications to various existing 600V MCC's in Section 1 & 2 Processes.

Headworks Building, including:
- Installation of new Mechanical Step Screens
- Shaftless Spiral Transfer Conveyor
- Wash Press
- Screw Classifier
- Grit Classifier
- Vortex Grit Removal Systems
- Air Blowers
- Actuated Slide Gates
- Chemical Dosing Equipment including Polymer and Iron Salt System.

Inlet works also include new RPU, Instrument Control Panels ( ICP), PLC and SCADA Control and Integration
   
   
   
   
G.E. Booth (Lakeview) Wastewater Treatment Plant Improvements  
Location: Mississauga  |  Completed: 2015
Project Scope:
Miscellaneous Improvements to the existing plant, including;
- Removal of existing Chemically Enhanced Polymer Treatment system for the existing heating building
- Installation of the new CEPT system in both heating building and thermal conditioning facility
- Relocation of the existing diesel generator
- Construction of a new Oil Handling Facility within the vicinity of the Outfall Chamber
   
   
   
   
   
   
   
   
Greenway Pollution Control Plant Upgrades  
Location: London  |  Completed: Dec 2013
Project Scope:
Upgrades to the Existing Pollution Control Plant;
- Removal of the existing structural steel and the installation of 2 new concrete floors
- New equipment includes; decanter centrifuges,
- piston cake pumps,
- outdoor lime silo,
- conveyors,
- polymer system,
-centrate sampling systems,
- rotary lube pumps,
- centrifuge pumps
- ozone foul air treatment system

   
   
   
   
   
   
   
   
   
Molise Kleinburg Pumping Station  
Location: Kleinburg  |  Completed: Nov 2012
Project Scope:
Molise Kleinburg Pumping Station

Owner: Castlepoint Investments

Engineer: AECOM Canada Ltd.

Start Date: August 2011
Completion Date: November 2012

Description:
The project involved the construction of an 16.25 m x 8.8 m x 9.0 m deep wet well and a 143 m2 building. Due to the tight restrictions of the site, soldier pile and lagging system was utilized in order to complete the project. Installation of new submersible sewage pumps, process piping, valves, HVAC, plumbing, back-up diesel generator, instruments, electrical motor control centre, control panel and SCADA integration completed the work.

   
   
   
   
   
   
   
   
   
   
Tavistock WWTP - Upgrades and Expansion  
Location: Tavistock, Ontario  |  Completed: September 2011
Project Scope:
Construction of a new earth berm lagoon and sand filtration cells. Construction also includes large earth moving operations, installation of new sanitary sewers connecting existing services, new primary hydro pole line service, aeration piping, pumping station and chemical building.
   
   
   
   
Jennings Creek Sewage Pumping Station  
Location: Lindsay  |  Completed: Dec 2013
Project Scope:
Jennings Creek Sewage Pumping Station

Owner: City of Kawartha Lakes

Engineer: Stantec Consulting Ltd.

Start Date: December 2011
Completion Date: 90% Complete

Description:
The project involved the construction of an 8.0 m x 5.7 m x 15.5 m deep wet well and a 35 m2 separate electrical building. Installation of new submersible sewage pumps, process piping, valves, HVAC, plumbing, back-up diesel generator, instruments, electrical motor control centre, control panel and SCADA integration completed the work.

   
   
   
   
   
   
   
   
   
Gore Road Sewage Pumping Station and Forcemain  
Location: Brampton  |  Completed: June 2010
Project Scope:
Gore Road Sewage Pumping Station and Forcemain

Owner: Region of Peel

Engineer: Gamsby and Mannerow Engineers

Start Date: August 2009
Completion Date: June 2010

Description:
The project involved the construction of a new wet well and control building, installation of new submersible pumps, process piping, valve chamber back-up diesel generator, electrical motor control centre, control panels and instrumentation with PLC and SCADA integration. Directional drilling and installation of 1.4 km of HDPE force-main piping for the new pumping station was also completed.

   
   
Brownley Well House and Water-main Upgrades  
Location: Angus/Essa  |  Completed: May 2009
Project Scope:
Brownley Well House and Water-main Upgrades
Owner: Town of Angus / Essa Township
Start Date: March 2008
Completion Date: May 2009

Description:
The project involved construction of a new pumping station consisting of concrete foundation, masonry walls and wood framed roof. Process equipment consisted of deep well pumps, process piping, valves, in-line UV disinfecting equipment, chemical dosing equipment, back-up diesel generator, electrical motor control centres, instrumentation and controls complete with SCADA integration.

Lake Street Sewage Pumping Station Upgrade  
Location:   |  Completed: April 2012
Project Scope:
Lake Street Sewage Pumping Station Upgrade
Owner: Niagara Region

Engineer: AECOM Canada Ltd.

Start Date: January 2009
Completion Date: April 2012

Description:
The project involved removal and replacement of the existing dry pit pumps, process valves, instruments and electrical switch gear. The contract also required the installation of a new concrete valve chamber, HVAC upgrades, replacement of the existing flat roof with pre-engineered trusses and miscellaneous architectural upgrades to existing interior finishes. All process upgrades were completed while using temporary pumps and controls to completely by-pass the pumping station flow of 400 l/s.


Hillsburgh Booster Pumping Station  
Location: Hillsburgh, Near Erin  |  Completed: Winter 2014
Project Scope:
- New Pre-cast concrete building and trussed roof
- New Access driveway, security fencing and gate
- Installation of Class 2 Greywater system(drainage pit)
- New high lift pumps with variable speed drives
- Dual concrete headwalls and storm culvert
- New HVAC, electrical and control instrumentation
   
   
   
   
   
   
   
   
   
   
   
   
Woodward Ave Pumping Station & RAS Chlorination  
Location: Hamilton  |  Completed: May 2010
Project Scope:
Woodward Ave. Effluent Pumping Station and RAS Chlorination

Owner: City of Hamilton

Engineer: Hydromantis Inc.

Start Date: January 2009
Completion Date: May 2010

Description:
The project involved installation of underground chlorine gas piping, effluent water distribution piping, chlorine gas injectors and diffusers. Complete refurbishment of existing effluent water pumping station while maintaining continuous operation. This included the removal and replacement of automatic strainers, process piping, valves, pumps, electrical motor control centre, control panels and instruments.